The approval and construction timeline

Dated public record

Reviewed through November 8, 2026. The site plan was approved and construction is underway. These cited editorial entries are separate from the live community event tools below. A scheduled inspection is not a completed result.

  1. City says no Wetlands Board permit is required

    The City’s letter concludes that the proposed impacts do not require local Wetlands Board approval. It also says other agency authorizations may be required. The revised February 11 plans were already in the file.

  2. Corps verifies NWP 7 and 18 coverage

    The verification lists pond, fringe-wetland and outfall impacts, subject to its conditions. It expressly says the letter does not confirm the submitted wetland delineation. It states no pond-fill cubic-yard total; the NWP 18 text’s 25-cubic-yard criterion is not a measurement of this project’s fill.

  3. Engineering memo: “cannot be approved”

    The sixth-review memo still requires an updated owner flooding acknowledgment and 10- and 100-year ponding exhibit. Several variance requests are “acceptable in concept” but not yet approved.

  4. Next-day memo: “approved”

    The revised memo says the plan is approved. The repeated flooding-acknowledgment demand is removed, and “acceptable in concept” becomes “acceptable.” The produced file does not establish that a new acknowledgment was supplied between these memos.

  5. Site plan approved; release conditions remain

    The City approves Solara at Shadowlawn. The letter separates site-plan approval from release for construction and requires recorded agreements, permits, sureties and a preconstruction meeting before work.

  6. Stormwater maintenance agreement recorded

    The produced recording identifies instrument 202603048395, October 1 at 3:25 p.m. This is after July’s site-plan approval and one day before the LDSW permit. The underlying nutrient-credit/financial bundle is not republished.

    • Recorded instrument 202603048395, p. 1 — F022866, 202603048395__1_ (1).pdf, recording stamp as documented in received-records-audit.md §5.1 item 5 and §5.2 F5; November 5 production.
  7. Land-disturbance / stormwater permit issued

    Permit 2026-DSC-023798 identifies Shadowlawn Associates LLC as owner, Beach Building Group Inc. as developer, and 24 units. Its project-name field says “Site Plan for Salt at Shadowlawn.”

    • City land-disturbance permit, October 2, 2026 — L07-021142-LDSW_permit_and_documents.pdf, p. 1; record 2026-DSC-023798, produced in F022866 on November 5. The source contains personal/certificate details and is not republished here.
  8. Rain-event inspection records flooding before work

    The E&S rain-event result is Failed and says no work had begun and there were already flooding concerns. A separate E&S inspection the same day Passed. These are distinct inspection results, not a determination here of a permit violation.

  9. Inspector records excavator fire and “Fix and Proceed”

    The inspector notes emergency response during demolition, says foam was contained on site, and says chemical use will be documented in the contractor’s SWPPP book. The note is not that log; foam type, quantity and spill-notification records remain unresolved.

  10. DEQ replaces the January waiver basis

    DEQ’s replacement letter selects NWP authorization under box A.6 rather than the earlier local/VMRC-permit basis. DEQ’s written response says that earlier basis was an assumption. This chronology does not decide the legal effect of either letter.

  11. F022755: City releases 23 files

    The first City tranche includes the approval letter, wetland plans and Corps verification. The City calls its response complete; the requester’s record review identifies remaining gaps.

    • FOIA status review, November 8, 2026 — Received-records audit, November 5, Parts 4–5, and Jeffrey Werby’s November 8 verified request-status update. Agency closure and unresolved production gaps are tracked separately.
  12. F022803: free tranche; further work behind deposit

    The City releases inspection, permit and other records without charge, but requests a $481.65 deposit for further review/search work, including a $130 Hickory storage/retrieval charge for a file included in the free tranche.

  13. F022866: 141 files released

    The later tranche brings the July engineering memos, permit documents and an updated inspection CSV. Some items remain missing or partial, with some fully black pages. The produced CSV stops before the November 8 portal snapshot and is not its source.

    • FOIA status review, November 8, 2026 — Received-records audit, November 5, Parts 4–5, and Jeffrey Werby’s November 8 verified request-status update. Agency closure and unresolved production gaps are tracked separately.
  14. Dated snapshot

    Dated permit snapshot: civil Active; wall Ready to Issue

    Construction is underway. CIVL-26157 shows six Passed, one Failed, one Fix and Proceed and one Not Ready completed inspection; latest completed pass November 5. BDRA-28536 is Ready to Issue with $1,871.50 outstanding on invoice 1165764 dated November 4. These are statuses, not violations.

  15. Scheduled, not completed

    Scheduled E&S inspection — not completed

    Inspection 5470033 is scheduled for November 12, time TBD, inspector Terice A Mason. This is a future appointment in the November 8 snapshot, not a completed inspection or result.

Community events and hearing tools

Admin-published event entries remain available with their detail pages. Past dates are historical entries, not a notice of a current hearing.

No upcoming admin-published event is listed. Historical event records remain below.

Monday, February 24, 2025
ETS Infiltration Testing — Zero Infiltration FoundEventHistorical event — not current
Friday, April 11, 2025
1st City Review — Deficiencies IdentifiedDeadlineHistorical event — not current
Thursday, April 17, 2025
Site Plan 1st SubmittalEventHistorical event — not current
Thursday, April 17, 2025
Project Narrative Filed — 24 Units ConfirmedEventHistorical event — not current
Monday, May 19, 2025
City Review 1 — First Round CommentsEventHistorical event — not current
Friday, July 11, 2025
2nd City Review — Deficiencies PersistDeadlineHistorical event — not current
Thursday, July 24, 2025
Site Plan 2nd SubmittalEventHistorical event — not current
Wednesday, August 20, 2025
City Review 2 — Second Round CommentsEventHistorical event — not current
Friday, October 10, 2025
Developer Comment Response (October)EventHistorical event — not current
Friday, October 10, 2025
3rd City Review — Multiple Deficiencies RemainDeadlineHistorical event — not current
Tuesday, November 11, 2025
Site Plan 3rd SubmittalEventHistorical event — not current
Monday, December 15, 2025
3rd Submittal Revised — Traffic Engineering DisapprovesEventHistorical event — not current
Tuesday, December 16, 2025
City Review 3 — Third Round CommentsEventHistorical event — not current
Thursday, January 15, 2026
Wetlands/Tidal Resource Application FiledEventHistorical event — not current
Thursday, February 5, 2026
Developer Comment Response (February)EventHistorical event — not current
Thursday, February 5, 2026
4th Submittal — Under ReviewDeadlineHistorical event — not current
Friday, February 20, 2026
Wetlands Board — No Permit Required LetterEventHistorical event — not current
Saturday, February 28, 2026
Community Petition LaunchedEventHistorical event — not current
Wednesday, March 4, 2026
Shadowlawn Civic MeetingHearingHistorical event — not current
Friday, March 6, 2026
City Review 4 — Fourth Round CommentsEventHistorical event — not current
Monday, March 16, 2026
Site Plan 4th SubmittalEventHistorical event — not current
Sunday, March 29, 2026
Formal Opposition Point Paper PublishedEventHistorical event — not current
Sunday, March 29, 2026
Community Review Published — 13 Grounds DocumentedEventHistorical event — not current
Tuesday, March 31, 2026
Planning Staff Update MeetingHearingHistorical event — not current
Tuesday, March 31, 2026
Civic League Q&A with Planning StaffHearingHistorical event — not current
Friday, May 1, 2026
Planning Commission HearingHearingHistorical event — not current