The approval and construction timeline
Dated public record
Reviewed through November 8, 2026. The site plan was approved and construction is underway. These cited editorial entries are separate from the live community event tools below. A scheduled inspection is not a completed result.
City says no Wetlands Board permit is required
The City’s letter concludes that the proposed impacts do not require local Wetlands Board approval. It also says other agency authorizations may be required. The revised February 11 plans were already in the file.
- Heaven Manning letter, February 20, 2026 — 2026-WTRA-00009_Shadowlawn_Associates_LLC_1001_Virginia_Ave_NPR.pdf, p. 1.
Corps verifies NWP 7 and 18 coverage
The verification lists pond, fringe-wetland and outfall impacts, subject to its conditions. It expressly says the letter does not confirm the submitted wetland delineation. It states no pond-fill cubic-yard total; the NWP 18 text’s 25-cubic-yard criterion is not a measurement of this project’s fill.
- NAO-2026-00081 verification and NWP 18 — City-produced Corps package, pp. 1–3 and 96; selected plan pages 8–10 are included for context.
Engineering memo: “cannot be approved”
The sixth-review memo still requires an updated owner flooding acknowledgment and 10- and 100-year ponding exhibit. Several variance requests are “acceptable in concept” but not yet approved.
- E.J. Gwin sixth-review memo, July 7, 2026 — L07-021142-SP_Solara_at_Shadowlawn_6th_Review-EG__4_.docx; General Comments, produced November 5.
Next-day memo: “approved”
The revised memo says the plan is approved. The repeated flooding-acknowledgment demand is removed, and “acceptable in concept” becomes “acceptable.” The produced file does not establish that a new acknowledgment was supplied between these memos.
- E.J. Gwin sixth-review memo, July 8, 2026 — L07-021142-SP_Solara_at_Shadowlawn_6th_Review-EG.docx (also duplicated as __3_); opening and General Comments.
Site plan approved; release conditions remain
The City approves Solara at Shadowlawn. The letter separates site-plan approval from release for construction and requires recorded agreements, permits, sureties and a preconstruction meeting before work.
- City site-plan approval, July 24, 2026 — 20260724-PLN-L07-021142-SP_1001_Virginia_Ave_Approval-LTR.pdf, pp. 1–3; produced in F022755 on October 21.
Stormwater maintenance agreement recorded
The produced recording identifies instrument 202603048395, October 1 at 3:25 p.m. This is after July’s site-plan approval and one day before the LDSW permit. The underlying nutrient-credit/financial bundle is not republished.
- Recorded instrument 202603048395, p. 1 — F022866, 202603048395__1_ (1).pdf, recording stamp as documented in received-records-audit.md §5.1 item 5 and §5.2 F5; November 5 production.
Land-disturbance / stormwater permit issued
Permit 2026-DSC-023798 identifies Shadowlawn Associates LLC as owner, Beach Building Group Inc. as developer, and 24 units. Its project-name field says “Site Plan for Salt at Shadowlawn.”
- City land-disturbance permit, October 2, 2026 — L07-021142-LDSW_permit_and_documents.pdf, p. 1; record 2026-DSC-023798, produced in F022866 on November 5. The source contains personal/certificate details and is not republished here.
Rain-event inspection records flooding before work
The E&S rain-event result is Failed and says no work had begun and there were already flooding concerns. A separate E&S inspection the same day Passed. These are distinct inspection results, not a determination here of a permit violation.
- 2026-CIVL-26157 inspection log, October 23 production — 2026-CIVL-26157_insp.csv, October 13 E&S and E&S – Rain Event rows.
Inspector records excavator fire and “Fix and Proceed”
The inspector notes emergency response during demolition, says foam was contained on site, and says chemical use will be documented in the contractor’s SWPPP book. The note is not that log; foam type, quantity and spill-notification records remain unresolved.
- Civil inspection log, October 16 result — 2026-CIVL-26157_insp.csv, Fix and Proceed row.
DEQ replaces the January waiver basis
DEQ’s replacement letter selects NWP authorization under box A.6 rather than the earlier local/VMRC-permit basis. DEQ’s written response says that earlier basis was an assumption. This chronology does not decide the legal effect of either letter.
- DEQ NPR letter, October 20, pp. 1–3 — 26-0055_20261020_DEQ NPR Letter.pdf; box A.6 on p. 3. DEQ explanation documented in the November 5 received-records audit, Finding 3.
F022755: City releases 23 files
The first City tranche includes the approval letter, wetland plans and Corps verification. The City calls its response complete; the requester’s record review identifies remaining gaps.
- FOIA status review, November 8, 2026 — Received-records audit, November 5, Parts 4–5, and Jeffrey Werby’s November 8 verified request-status update. Agency closure and unresolved production gaps are tracked separately.
F022803: free tranche; further work behind deposit
The City releases inspection, permit and other records without charge, but requests a $481.65 deposit for further review/search work, including a $130 Hickory storage/retrieval charge for a file included in the free tranche.
- City estimate INV26-F022803-1, October 23, 2026; status verified November 8 — Invoice_INV26-F022803-1.pdf, p. 1 (reviewed; personal billing details omitted); received-records audit Part 4 and October 23 City response.
F022866: 141 files released
The later tranche brings the July engineering memos, permit documents and an updated inspection CSV. Some items remain missing or partial, with some fully black pages. The produced CSV stops before the November 8 portal snapshot and is not its source.
- FOIA status review, November 8, 2026 — Received-records audit, November 5, Parts 4–5, and Jeffrey Werby’s November 8 verified request-status update. Agency closure and unresolved production gaps are tracked separately.
- Dated snapshot
Dated permit snapshot: civil Active; wall Ready to Issue
Construction is underway. CIVL-26157 shows six Passed, one Failed, one Fix and Proceed and one Not Ready completed inspection; latest completed pass November 5. BDRA-28536 is Ready to Issue with $1,871.50 outstanding on invoice 1165764 dated November 4. These are statuses, not violations.
- Permit portal snapshot verified by Jeffrey Werby, November 8, 2026 — User-verified dated snapshot supplied for this update; not a live portal feed and not the older October inspection CSV.
- Scheduled, not completed
Scheduled E&S inspection — not completed
Inspection 5470033 is scheduled for November 12, time TBD, inspector Terice A Mason. This is a future appointment in the November 8 snapshot, not a completed inspection or result.
- Permit portal snapshot verified by Jeffrey Werby, November 8, 2026 — User-verified dated snapshot supplied for this update; not a live portal feed and not the older October inspection CSV.
Community events and hearing tools
Admin-published event entries remain available with their detail pages. Past dates are historical entries, not a notice of a current hearing.
No upcoming admin-published event is listed. Historical event records remain below.