Curated editorial summary · reviewed November 8, 2026. This is not an original agency document, legal advice, or a live status feed.
Sources: received-records-audit.md, prepared November 5, 2026, Part 4 request tracker and Part 5 production scorecard, together with Jeffrey Werby’s verified November 8 status update. The audit is research support, not an agency finding; raw correspondence bundles are not republished.
City of Virginia Beach: F022755
Closed by City; gaps remain · Filed October 6, 2026
The City says its response is complete. It released 23 files on October 21 and stated that staff did not visit the site for the wetlands determination. The SWMA missing from this tranche later appeared in other productions.
Still unresolved: Numbered DSC documents, cut/fill and finished-floor information, and internal WTRA review notes remain unresolved in the review. An agency closure is not a finding that every requested record was produced.
Source: Received-records audit, November 5, Parts 4–5, and Jeffrey Werby’s November 8 verified request-status update. Agency closure and unresolved production gaps are tracked separately.
City of Virginia Beach: F022803
Partial; on hold for $481.65 deposit · Filed October 13, 2026
A free production was released October 23. Further email review and DSC searching are on hold pending a $481.65 deposit: $207.17 for attorney review, $144.48 for DSC work, and $130 for off-site Hickory file storage/retrieval. That Hickory file was already included in the free batch.
Still unresolved: Additional email and DSC records remain behind the deposit. The City said its response clock was tolled pending payment; this page does not label the request overdue.
Source: Invoice_INV26-F022803-1.pdf, p. 1 (reviewed; personal billing details omitted); received-records audit Part 4 and October 23 City response.
City of Virginia Beach: F022866
Answered November 5; incomplete in review · Filed October 19, 2026
The November 5 response contained 141 files, including duplicates, engineering reviews, permit material, and later inspection records. Some produced pages are fully blacked out. The review also found inconsistent handling of attorney-client markings; privileged email bodies are not republished here.
Still unresolved: Tidal-datum analysis, the +3.22-foot wetland-impact review, survey field data, and the contractor’s foam/SWPPP log were not produced. City model files, ponding acknowledgments, variance findings and workflow history remain partial or unresolved. These are production gaps, not legal conclusions about withholding.
Source: Received-records audit, November 5, Parts 4–5, and Jeffrey Werby’s November 8 verified request-status update. Agency closure and unresolved production gaps are tracked separately.
Virginia DEQ · NextRequest: 26-5812
Closed October 13 as released in full; gaps remain · Filed October 6, 2026
DEQ closed the request October 13 as released in full. The January 14, 2026 waiver letter is in hand. DEQ separately supplied written answers and a replacement no-permit-required letter on October 20.
Still unresolved: The Additional Data Needs PDF, records after January 28, waiver-review notes, DEQ nutrient/offset records, and fill/flood-storage information remain missing or unresolved in the requester’s review.
Source: Received-records audit, November 5, Parts 4–5, and Jeffrey Werby’s November 8 verified request-status update. Agency closure and unresolved production gaps are tracked separately.
U.S. Army Corps of Engineers: FA-26-F0007
Pending; no FOIA production as of November 8 · Filed October 13, 2026
Filed October 13 and clarified October 16; a tracking number was provided October 19. The approximate 20-working-day mark is November 10, not a declaration here of a legal deadline or violation.
Still unresolved: The decision file, delineation/site-visit review, fill-volume information and coordination records remain awaited. The April 13 NWP 7 and 18 verification for NAO-2026-00081 is already in hand from other productions; it was not produced under this FOIA request.
Source: Received-records audit, November 5, Parts 4–5, and Jeffrey Werby’s November 8 verified request-status update. Agency closure and unresolved production gaps are tracked separately.
Deposit evidence, without personal billing details
Reviewed original: Invoice_INV26-F022803-1.pdf, p. 1, estimate INV26-F022803-1, dated October 23, 2026, request F022803-101326. Total $481.65: City Attorney $207.17; Planning/Development Services Center $144.48; off-site storage and retrieval fee $130.00. The billing name and payment/remittance instructions are omitted from this summary. The connection to the Hickory file and the response-clock hold is documented in the October 23 City response and the received-records audit, Parts 2 and 4.