2026-CIVL-26157 Active
Completed inspections: Passed 6 · Failed 1 · Fix and Proceed 1 · Not Ready 1.
Latest completed pass: .
Next E&S inspection: November 12, 2026
5470033 · TBD · Terice A Mason
Scheduled — not completed.
Five requests, their agency response statuses, and the records still unresolved in our review.
Curated tracker as of November 8, 2026, separate from additional admin-published entries below. “Closed” describes the agency’s status; it does not mean every question is resolved. Missing records and redactions are not labeled legal violations here.
Closed by City; gaps remain
The City says its response is complete. It released 23 files on October 21 and stated that staff did not visit the site for the wetlands determination. The SWMA missing from this tranche later appeared in other productions.
Still unresolved: Numbered DSC documents, cut/fill and finished-floor information, and internal WTRA review notes remain unresolved in the review. An agency closure is not a finding that every requested record was produced.
Source: FOIA status review, November 8, 2026. Received-records audit, November 5, Parts 4–5, and Jeffrey Werby’s November 8 verified request-status update. Agency closure and unresolved production gaps are tracked separately.
Partial; on hold for $481.65 deposit
A free production was released October 23. Further email review and DSC searching are on hold pending a $481.65 deposit: $207.17 for attorney review, $144.48 for DSC work, and $130 for off-site Hickory file storage/retrieval. That Hickory file was already included in the free batch.
Still unresolved: Additional email and DSC records remain behind the deposit. The City said its response clock was tolled pending payment; this page does not label the request overdue.
Source: City estimate INV26-F022803-1, October 23, 2026; status verified November 8. Invoice_INV26-F022803-1.pdf, p. 1 (reviewed; personal billing details omitted); received-records audit Part 4 and October 23 City response.
Answered November 5; incomplete in review
The November 5 response contained 141 files, including duplicates, engineering reviews, permit material, and later inspection records. Some produced pages are fully blacked out. The review also found inconsistent handling of attorney-client markings; privileged email bodies are not republished here.
Still unresolved: Tidal-datum analysis, the +3.22-foot wetland-impact review, survey field data, and the contractor’s foam/SWPPP log were not produced. City model files, ponding acknowledgments, variance findings and workflow history remain partial or unresolved. These are production gaps, not legal conclusions about withholding.
Source: FOIA status review, November 8, 2026. Received-records audit, November 5, Parts 4–5, and Jeffrey Werby’s November 8 verified request-status update. Agency closure and unresolved production gaps are tracked separately.
Closed October 13 as released in full; gaps remain
DEQ closed the request October 13 as released in full. The January 14, 2026 waiver letter is in hand. DEQ separately supplied written answers and a replacement no-permit-required letter on October 20.
Still unresolved: The Additional Data Needs PDF (RRS_DEQ_Additional_Data_Needs_Virginia_Ave.pdf) and records after January 28, 2026 remain missing; a follow-up posted October 16 was not addressed.
Source: FOIA status review, November 8, 2026. Received-records audit, November 5, Parts 4–5, and Jeffrey Werby’s November 8 verified request-status update. Agency closure and unresolved production gaps are tracked separately.
Pending; no FOIA production as of November 8
Filed October 13 and clarified October 16; a tracking number was provided October 19. The approximate 20-working-day mark is November 10, not a declaration here of a legal deadline or violation.
Still unresolved: The decision file, delineation/site-visit review, fill-volume information and coordination records remain awaited. The April 13 NWP 7 and 18 verification for NAO-2026-00081 is already in hand from other productions; it was not produced under this FOIA request.
Source: FOIA status review, November 8, 2026. Received-records audit, November 5, Parts 4–5, and Jeffrey Werby’s November 8 verified request-status update. Agency closure and unresolved production gaps are tracked separately.
Snapshot verified November 8, 2026. Status information, not a finding of a violation. Not a live portal feed.
Completed inspections: Passed 6 · Failed 1 · Fix and Proceed 1 · Not Ready 1.
Latest completed pass: .
Next E&S inspection: November 12, 2026
5470033 · TBD · Terice A Mason
Scheduled — not completed.
Retaining wall / building addition-alteration · Beach Building Group.
$1,871.50 outstanding
Invoice 1165764, dated November 4, 2026.
“Ready to Issue” is not the same as an issued permit.
Source: Permit portal snapshot verified by Jeffrey Werby, November 8, 2026. The older FOIA inspection CSVs do not contain this later tally.
The July 24 approval calls the project “Solara at Shadowlawn,” formerly Virginia Avenue Condo. The October 2 land-disturbance permit uses “Site Plan for Salt at Shadowlawn” and identifies Shadowlawn Associates LLC as current owner and Beach Building Group Inc. as developer. These are the names in those records; they are not replaced with “Shadowlawn North, LLC.”
These database entries keep their document counts, deadlines and request detail tools. An empty list here does not mean there are no pending requests in the dated tracker above.
No additional admin-published entries match this view. The five-request review above remains available.