Record reviewed through . Not a live permit feed.
The Record
What the public records show about the approval and construction at 1001 Virginia Avenue. Compare the record with a rule or the City’s own written requirement, then read the gap and the source. Each issue opens a four-part account with its limits intact.
Status meanings and full-inventory counts
- Documented contradiction (15)
- Two records, or a record and a stated requirement, do not align. This is not a legal finding.
- Named in request but not produced (11)
- The item was requested by name or plain wording and has not appeared in the productions held. It may exist elsewhere.
- Agency said no records (1)
- The agency expressly said the particular requested record does not exist. This does not describe every record on the topic.
- Reported, not proven (1)
- An individual report without a confirming agency record. Timing and causation may be unverified.
- Incomplete / still investigating (7)
- The available facts are partial. A pending record, field question or unverified requirement could change the assessment.
Issue matrix
5 of 35 issues shown
Open an issue for its record, requirement, gap and citations. Scroll the table sideways on small screens.
| Issue | Topic / jurisdiction | Status | Mismatch or open question | Source |
|---|---|---|---|---|
| S1 Bigger pipe, more water toward the ditches: the developer’s lawyer said no added burden; the City Attorney said otherwise | Stormwater & floodingCity | Documented contradiction | The two released letters describe the off-site drainage burden differently. The engineering and property-rights questions are not settled by either letter. No new flood or causation finding is made here. | Holleran-Taylor_7-31-2025.PDF2025-07-31 · Page unavailable in this copy; also Release.pdf pp. 17–19All citations for S1 |
| S2 The flood-analysis variance changed from unsupported to acceptable; no separate findings were produced | Stormwater & floodingVirginia · City | Named in request but not produced | The City’s stated position changed in about seven weeks. The approval records do not set out findings addressing the exception criteria, and no stand-alone exception record was produced. The model figures are reported for comparison, not as an independent engineering finding or a legal conclusion. | 20260520-PLN-L07-021142-SP_1001_Virginia_Ave_Review5-LTR.docx2026-05-20 · Page unavailable; combined flood-analysis commentAll citations for S2 |
| S3 The project must show no increased flooding through the City’s drainage study; no City model files were produced | Stormwater & floodingCity | Named in request but not produced | No City model inputs, outputs, run logs, maps or reconciliation memo were produced. The produced emails and developer model do not document a separate City run. Non-production does not establish that the files never existed or that the project will increase flooding. | RE__Proposed_development_at_1001_Virginia_Ave__DSC_File_L07-021142-SP_.pdf2026-03-03 · Embedded email p. 5 (Logan, February 27, 2026)All citations for S3 |
| S4 Agreement and easement milestones followed approval; submission and recording are different conditions | Stormwater & floodingCity | Documented contradiction | Easement recordation came after the stated pre-approval deadline. The maintenance agreement was not final at approval, but the City’s pre-approval requirement was submission, not recordation: the records summarized here do not establish its initial submission date. Its separate recording-before-release condition was met. Later recording must not be described as failure to record. | 20250519-PLN-L07-021142-SP-Review1-LTR.docx2025-05-19 · Page unavailable; agreement and easement commentsAll citations for S4 |
| S5 The approved design removes pond storage; no tidal or compensatory-storage analysis was produced | Stormwater & floodingCity · Virginia | Named in request but not produced | The produced storm manual provides rainfall modeling, but no identified tidal-boundary, compensatory-storage or no-rise analysis. The City did not say that none exist. This does not establish the amount of storage actually removed or an engineering finding about future flooding. | 20250519-PLN-L07-021142-SP-Review1-LTR.docx2025-05-19 · Page unavailable; pond-storage commentAll citations for S5 |
Sources, method and limits
This is a neighborhood advocacy site’s inventory of received public records, not an independent engineering review, agency determination or legal advice. “Documented contradiction” describes records that do not align; it does not mean a court or agency found a violation. A missing record is not proof that it never existed.
The inventory uses the October 21 City F022755 review, the November 5 received-records audit, the November 8 case inventory and dated permit snapshots. PDF page references use the original file’s page index; portfolio email pages are labeled separately. Excerpts retain visible original page references. Source notes distinguish official text checked by the earlier review, staff-cited requirements, OCR and unverified questions. This update did not independently recheck every statute, page image or live agency system.
Where a document date or page could not be grounded, the citation says unavailable or unpaginated rather than guessing. A linked document may be a safe excerpt or source summary; other citations lead to the curated recent records library, not a promise that the entire original file is public here. Original filenames remain visible.
Bank information, redacted personal details, unrelated-project personal details, unsent drafts and privileged email bodies are not republished. Nothing beneath a redaction is reconstructed. Conclusions about wetland jurisdiction, engineering adequacy, property rights and damage causation remain unresolved where the record says so.